Fallon Park Elementary Construction
Posted on 10/12/2018
New academic building at the new Fallon Park Elementary in Octdober, 2018
Here is a September 27 update:

The rain has been an issue but work continues on Phase 1.   It includes a two story building that will house 26 classrooms.  Crews have completed the electrical, plumbing, and HVAC on the first floor.  They are now working to install the roof.  Soon, crews will install the final steel roof deck for the media center. 

In the coming weeks, crews will demolish the second modular classroom.  This will allow Phase 2 to get underway.

The new school will be completed in three phases.  Phase 1 is scheduled to be finished in early 2019.  The 26 classroom wing building is being built behind the current school.

Phase 2 will include a new cafeteria, administrative offices, and a two-story wing with additional classrooms.  Phase 2 is scheduled to be completed by December 2019.

Phase 3 includes the demolition of the existing school building, the construction of the new bus loop, the renovation of the existing gym, and the conversion of the existing cafeteria into an art and music center.  Phase 3 is scheduled to be completed in the summer of 2020.

Artist rendition of the new Fallon Park Elementaryartist rendition of the new Fallon Park Elementary, shows the entire school


Students will remain in the current facility during construction.  They will move in as each phase is completed.  

These are pictures from October 2, 2018

shot of the new media center under constructionshot of the new media center from the outside of the buildingback side of the new Fallon Park Elementaryentrance to the new academic building at Fallon Park Elementary


These are pictures from August 25, 2018

front facade of the new academic buildingwindow frame, showing the mountains in the backgroundnew media center under constructionconstruction worker welding inside new Fallon Park Elementary



These pictures are from July 31, 2018:

The gront facade of the new academic buildingscafolding in front of the new FalloN Park Elementary


These pictures are from July 12, 2018:

Constrution of the new Fallon Park Elementary, the new academic buildingPicture of the new Fallon Park Elementary with the mountains in the backgroundA classroom under construction for the new Fallon Park Elementarysoon to be window at new Fallon Park Elementary, shows the mountains in the background



These pictures are from June 21, 2018:

The supporting walls of the new Fallon Park ElementaryThe new facility being built, picture taken from the Fallon Park picnic shelter



These pictures are from June 12, 2018

Construction crews working on the new Fallon Park Elementary, retaining walls are in the backgroundA stairway under construction for the new Fallon Park ELementaryA hallway taking shape inside the new 26 classroom wingthe old employee parking lot is now a pile of dirt


These are pictures from the week of May 21st.

the first floor framing of the new Fallon Park ElementaryConcrete foundation for the new 26 classroom wing






40 Douglass Avenue NW, Roanoke, VA24012 Phone 540-853-2502