Fallon Park Elementary Construction
Posted on 08/31/2018
aerial view of the construction at the new Fallon Park Elementary
Here is an August 27 update:

Fallon Park staff is using the new parking lot.  The underground utilities have been installed in the mechanical/electrical room.


The first phase includes a two-story building that will house 26 classrooms.  It is being built behind the current school.  Crews are installing the roof and in the interior wall framing on the second floor.  They will soon pour the concrete slab for the media center.  They've also started installing the windows.

The new school will be completed in three phases.  Phase 1 is scheduled to be finished in early 2019.  The 26 classroom wing building is being built behind the current school.

Phase 2 will include a new cafeteria, administrative offices, and a two-story wing with additional classrooms.  Phase 2 is scheduled to be completed by December 2019.

Phase 3 includes the demolition of the existing school building, the construction of the new bus loop, the renovation of the existing gym, and the conversion of the existing cafeteria into an art and music center.  Phase 3 is scheduled to be completed in the summer of 2020.

Artist rendition of the new Fallon Park Elementaryartist rendition of the new Fallon Park Elementary, shows the entire school


Students will remain in the current facility during construction.  They will move in as each phase is completed.  

These are pictures from August 25, 2018

front facade of the new academic buildingwindow frame, showing the mountains in the backgroundnew media center under constructionconstruction worker welding inside new Fallon Park Elementary



These pictures are from July 31, 2018:

The gront facade of the new academic buildingscafolding in front of the new FalloN Park Elementary


These pictures are from July 12, 2018:

Constrution of the new Fallon Park Elementary, the new academic buildingPicture of the new Fallon Park Elementary with the mountains in the backgroundA classroom under construction for the new Fallon Park Elementarysoon to be window at new Fallon Park Elementary, shows the mountains in the background



These pictures are from June 21, 2018:

The supporting walls of the new Fallon Park ElementaryThe new facility being built, picture taken from the Fallon Park picnic shelter



These pictures are from June 12, 2018

Construction crews working on the new Fallon Park Elementary, retaining walls are in the backgroundA stairway under construction for the new Fallon Park ELementaryA hallway taking shape inside the new 26 classroom wingthe old employee parking lot is now a pile of dirt


These are pictures from the week of May 21st.

the first floor framing of the new Fallon Park ElementaryConcrete foundation for the new 26 classroom wing